Skip to content

Project Flowing Fountain — Expedition Two

2011-12-10

A week after Expedition One found me back out on Bayou Fountain and hungry for more.  I entered at my usual place and started downstream.  I arrived at blockage eight fresh and in good spirits, and I immediately went to work.

The work this time was a bit more intense than last time.  Tangles of limbs are much easier to work with than winch-requiring downed trunks, but it still felt like a productive day.

Expedition Two statistics:

  • Blockages cleared: 9
  • Miles navigable: 2.30 (added 0.88 miles)
  • Percent complete: 53.8% (added 20.8%)
  • Total man-hours: 15 (added 8 hours, 1 person)